Kunming Eight Sewage Plants Into Garden Open To The Community

Water Industry Network

HC : In recent years into the Dianchi Lake Sewage Volume change, which is the main city of Kunming, the sewage treatment capacity is a test. Yesterday, the Dianchi Lake Water Pollution Prevention Steering Group of experts the main city of Kunming research building sewage treatment plants, the steering group to check on comments, six sewage treatment plants and 2 Expansion of the new sewage treatment plants, to ensure that the water index has reached an A standard, to build a sewage treatment plant garden, facing the open society, young people and members of the public, visitors to visit the sewage plant.

It is understood that the main city of Kunming, six wastewater treatment plant design sewage treatment capacity of 580,000 cubic meters, the water target to achieve a B standard. Sewage treatment plant is six ongoing Expansion, and New Japan for 20 million cubic meters of sewage treatment plants, and 10 seventh million cubic meters of sewage treatment plants eighth, Expansion, and the new sewage treatment plant to ensure that by the end of all test run. 2010 to change the sewage treatment plant expansion, new construction is completed, the main city of Kunming sewage treatment capacity will reach 1.105 million cubic meters daily processing capacity of the treated effluent standards up to an A standard.

North shore of Dianchi Lake in Kunming Water Environment Management Project is fully launched, a total investment of 3.975 billion yuan, mainly the new seventh and eighth sewage treatment plant sewage treatment plant, reconstruction and extension of other old sewage treatment plant. At the same time the main city of Kunming have started diverting sewage pipe trunk and branch sub-projects a total investment of 1.57 billion yuan, the project will be the new sewer network length of 336 km, after the completion of these projects, the main city of Kunming, the sewage treatment capacity will reach 110.5 million cu m / day, sewage collection rate of 95%.

Yesterday, the steering group of the starting first base along the side of Dianchi Lake Road to reach Haigeng seventh, eighth sewage treatment plant construction site to inspect the building, listen to reports. Then divided the steering group, separately inspected the first, second, third, fourth, fifth, sixth expansion of the sewage treatment plant to change the situation. In the survey, there are experts, the main city of Kunming, the sewage treatment plant are concentrated in the Dianchi Lake downstream to the upstream and middle reaches of the proposed plant site, cut off water, improve the urban landscape.

Forum held yesterday afternoon, the Steering Group heard north shore of Dianchi Lake in Yunnan Investment Corporation and the project leader to the report stressed the need to build a sewage treatment plant garden on the seventh and eighth sewage treatment plant outside Decoration Necessary adjustments to optimize the design, other wastewater treatment plant should be modified. In addition, except outside the main city of Kunming to other counties, such as Chenggong Town, Jinning, New District, Economic Development Zone and other places of the sewage treatment plant, and start planning as soon as possible and try to start in May next year.

North shore of Dianchi Lake project leader said, as at present, the first and second sewage treatment plant projects are completed 33% of the total project amount, 63.48%, the fourth sewage treatment plant construction has been basically completed; Third Sewage Treatment Plant Expansion early experience in civil engineering has been completed; the fifth, sixth sewage treatment plant expansion project were changed to complete 78%, 56%; VII of the completion of new sewage treatment plant 69.1% of the total project amount; VIII of the Civil sewage treatment plant unit Construction has been admitted. In addition, the sewage treatment plant will morph into popular garden park, which Yunnan will invest more than 3,000 investment companies million of the six sewage treatment plants to transform the landscape green.

It is reported that Yunnan Investment company has hosted the peace and other cities the sewage treatment plant at the same time take Panlong Town, Yunnan, Luquan County Yunlong Township sayingpan Township, A sub-camp of the construction of sewage treatment plant, currently Panlong Town, Yunnan, Luquan County Yunlong Township sayingpan Township has put into trial operation. In addition, the ninth being planned sewage treatment plant is still under Location.